Sparely
DU

THERMOWELL,DWG.112-4051,FOR TEL-1942-2

Material 4300067020 · THERMOWELL · Plant 1000

CMonitorStockout
Material
4300067020
Category
THERMOWELL
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
LANGIT SEJAHTERA PRATAMA PT
Lead time
95 d · P80 140 d
Unit price
Rp 9.6M

Recommendation

  • 1.Forecast 0.2 EA/year: 0.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~95 days; expected demand during lead time 0.1.
  • 3.A 94.9% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
Single sourceOpen PO
On hand / on order
0 / 2
next delivery 02 Mar 2027
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
94.9%
stockout risk now 0%
Unit price
Rp 9.6M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 261 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~43 days.

Installed on 1 functional locations

0 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TEL-1942-2
TEMPERATURE
C300.01

Lead time and procurement

Lead time 95 ± 40 days (PO history + category, 2 PO lines) · on-time 40%

PR dateTypeQtyUnit priceDeliveryLead time
30 Jul 2026PR03
Regular replenishment
2Rp 9.8M02 Mar 2027
open
215 d
28 Oct 2025PR06
Regular replenishment
1Rp 9.3M22 Nov 202525 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
13 Jan 20261201000032767Corrective