BEARING,THRUST PAD,DWG.490-3336,FOR KC-7

Material 4300068185 · BEARING · Plant 1000

AReorderCriticalStockout
Material
4300068185
Category
BEARING
Base unit
SET
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
55 d · P80 127 d
Unit price
Rp 219.3M (est.)

Recommendation

  • 1.Forecast 2.6 SET/year: 2.6 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~55 days; expected demand during lead time 0.4.
  • 3.A 98.4% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 4 now.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
4 SET
Rp 877.0M · order by 01 Oct 2026
Expected arrival ≈ 55 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
98.4%
stockout risk now 18%
Unit price
Rp 219.3M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 93 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 628.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-713B
SPENT CAUSTIC FAN
A163.14

Lead time and procurement

Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
17 Jun 2026LowPX_KC-713BLeak from packing
12 Jun 2026HighPX_KC-713BInspect coupling KC-713B
08 Apr 2026MediumPX_KC-713BInspect coupling KC-713B
13 Oct 2025EmergencyPX_KC-713BLeak from packing
29 Aug 2025LowPX_KC-713BLeak from packing
18 Jul 2025MediumPX_KC-713BOverhaul

Recent goods issues

Posting dateQtyOrderOrder type
30 Jun 20262201000037337Corrective