VALVE,GOVERNOR,DWG.398-6867,FOR KT-513

Material 4300069589 · VALVE · Plant 1000

ALong-leadReduceNon-moving
Material
4300069589
Category
VALVE
Base unit
ASS
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
RAJAWALI REFRAKTORI PRATAMA PT
Lead time
63 d · P80 92 d
Unit price
Rp 306.9M

Recommendation

  • 1.Forecast 0.1 ASS/year: 0.1 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~63 days; expected demand during lead time 0.0.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 5 exceeds the level to keep (0) by 5.
  • 5.Long lead time: 80% of deliveries took up to 92 days and the fastest seen in its category 20 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadConvert to Non StockSingle sourceOpen PO
On hand / on order
5 / 2
next delivery 07 Nov 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 306.9M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 26.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-513
TURBINE FOR KC-513
A121.53

Lead time and procurement

Lead time 63 ± 30 days (PO history + category, 1 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
20 Jul 2026PR03
Regular replenishment
2Rp 306.9M07 Nov 2026
open
110 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
04 Jan 2026MediumPX_KT-513KT-513 governor valve hunting
03 May 2025MediumPX_KT-513KT-513 governor valve hunting

Recent goods issues

Never issued in the 17-month history.