VALVE,GOVERNOR,DWG.605-4261,FOR KT-513
Material 4300070047 · VALVE · Plant 1000
AReorderCriticalStockout
- Material
- 4300070047
- Category
- VALVE
- Base unit
- ASS
- MRP type
- Stock Item
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 47 d · P80 92 d
- Unit price
- Rp 238.3M (est.)
Recommendation
- 1.Forecast 0.7 ASS/year: 0.7 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~47 days; expected demand during lead time 0.1.
- 3.A 91.7% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 1 now.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
1 ASS
Rp 238.3M · order by 01 Oct 2026
Expected arrival ≈ 47 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
91.7%
stockout risk now 8%
Unit price
Rp 238.3M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 222 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 284.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
Lead time and procurement
Lead time 47 ± 30 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 04 Jan 2026 | Medium | PX_KT-513 | KT-513 governor valve hunting |
| 03 May 2025 | Medium | PX_KT-513 | KT-513 governor valve hunting |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Feb 2026 | 1 | 201000019323 | Corrective |