SEAT RING,VALVE,DWG.910-7407,FOR FCV-283

Material 4300073565 · SEAT RING · Plant 1000

CReducePotentially obsolete
Material
4300073565
Category
SEAT RING
Base unit
EA
MRP type
Non Stock
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
SURYA ENERGI JAYA PT
Lead time
110 d · P80 184 d
Unit price
Rp 46.4M

Recommendation

  • 1.Forecast 0.0 EA/year: 0.0 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~110 days; expected demand during lead time 0.0.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 7 exceeds the level to keep (0) by 7.
Single sourceOpen POLead time estimated
On hand / on order
7 / 2
next delivery 24 Apr 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 46.4M
PO history
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 120,576/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~65 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-283B
SLOP OIL FLOW CONTROL
C100.11

Lead time and procurement

Lead time 110 ± 58 days (Category estimate, 0 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
06 Apr 2026PR10
Other
2Rp 46.4M24 Apr 2027
open
383 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Never issued in the 17-month history.