Sparely
DU

SEAT RING,VALVE,DWG.469-8754,FOR LCV-146

Material 4300074394 · SEAT RING · Plant 1000

CMonitorTAM reserve
Material
4300074394
Category
SEAT RING
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
SURYA PERKASA SENTOSA PT
Lead time
190 d · P80 273 d
Unit price
Rp 7.5M

Recommendation

  • 1.Forecast 0.0 EA/year: 0.0 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~190 days; expected demand during lead time 0.0.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Used only during the last turnaround (9 EA): keep it for the next one instead of treating it as slow-moving.
Last turnaround used 9Convert to Non StockSingle sourceOpen PO
On hand / on order
9 / 4
next delivery 28 Apr 2027
Today Min / Max
3 / 4
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 7.5M
PO history
ML early warning: 10% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (9 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 612,868/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~65 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_LCV-1465
LEVEL CONTROL VALVE
C110.55

Lead time and procurement

Lead time 190 ± 61 days (PO history, 4 PO lines) · on-time 25%

PR dateTypeQtyUnit priceDeliveryLead time
11 Sept 2026PR03
Regular replenishment
2Rp 7.6M20 Aug 2027
open
343 d
20 Apr 2026PR03
Regular replenishment
2Rp 7.5M28 Apr 2027
open
373 d
11 Sept 2025PR06
Regular replenishment
3Rp 7.4M23 Apr 2026224 d
10 Jul 2025PR03
Regular replenishment
2Rp 7.5M01 Feb 2026206 d
30 Jun 2025PR03
Regular replenishment
4Rp 7.4M11 Feb 2026226 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Jun 2025HighPX_LCV-1465[MSI-B-25-MDR-273/M] Replace line

Recent goods issues

Posting dateQtyOrderOrder type
30 Nov 20251203000009623Turnaround
30 Nov 20253203000009623Turnaround
29 Nov 20251203000009623Turnaround
27 Nov 20251203000009623Turnaround
27 Nov 20253203000009623Turnaround
Sparely