SEAT RING,VALVE,DWG.469-8754,FOR LCV-146
Material 4300074394 · SEAT RING · Plant 1000
CMonitorTAM reserve
- Material
- 4300074394
- Category
- SEAT RING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- C (0 of 1 FuncLocs A/B)
- Supplier
- SURYA PERKASA SENTOSA PT
- Lead time
- 190 d · P80 273 d
- Unit price
- Rp 7.5M
Recommendation
- 1.Forecast 0.0 EA/year: 0.0 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~190 days; expected demand during lead time 0.0.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
- 4.Used only during the last turnaround (9 EA): keep it for the next one instead of treating it as slow-moving.
Last turnaround used 9Convert to Non StockSingle sourceOpen PO
On hand / on order
9 / 4
next delivery 28 Apr 2027
Today Min / Max
3 / 4
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 7.5M
PO history
ML early warning: 10% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (9 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 612,868/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~65 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_LCV-1465 LEVEL CONTROL VALVE | C | 1 | 1 | 0.55 |
Lead time and procurement
Lead time 190 ± 61 days (PO history, 4 PO lines) · on-time 25%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 11 Sept 2026 | PR03 Regular replenishment | 2 | Rp 7.6M | 20 Aug 2027 open | 343 d |
| 20 Apr 2026 | PR03 Regular replenishment | 2 | Rp 7.5M | 28 Apr 2027 open | 373 d |
| 11 Sept 2025 | PR06 Regular replenishment | 3 | Rp 7.4M | 23 Apr 2026 | 224 d |
| 10 Jul 2025 | PR03 Regular replenishment | 2 | Rp 7.5M | 01 Feb 2026 | 206 d |
| 30 Jun 2025 | PR03 Regular replenishment | 4 | Rp 7.4M | 11 Feb 2026 | 226 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Jun 2025 | High | PX_LCV-1465 | [MSI-B-25-MDR-273/M] Replace line |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Nov 2025 | 1 | 203000009623 | Turnaround |
| 30 Nov 2025 | 3 | 203000009623 | Turnaround |
| 29 Nov 2025 | 1 | 203000009623 | Turnaround |
| 27 Nov 2025 | 1 | 203000009623 | Turnaround |
| 27 Nov 2025 | 3 | 203000009623 | Turnaround |