BEARING,JOURNAL,DWG.457-6962,FOR KC-853D

Material 4300074930 · BEARING · Plant 1000

BLong-leadReduceExcess
Material
4300074930
Category
BEARING
Base unit
SET
MRP type
Stock Item
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
RAJAWALI REFRAKTORI PRATAMA PT
Lead time
131 d · P80 127 d
Unit price
Rp 241.7M

Recommendation

  • 1.Forecast 0.8 SET/year: 0.8 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~131 days; expected demand during lead time 0.3.
  • 3.A 74.6% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.Stock 2 exceeds the level to keep (1) by 1.
  • 5.Long lead time: 80% of deliveries took up to 127 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
2 / 1
next delivery 22 Apr 2027
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
74.6%
stockout risk now 0%
Unit price
Rp 241.7M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 168 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 101.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~23 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-853D
SLOP OIL COMPRESSOR
B141.85

Lead time and procurement

Lead time 131 ± 40 days (PO history + category, 1 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
28 Apr 2026PR05
Project / turnaround
1Rp 239.4M22 Apr 2027
open
359 d
21 Jul 2025PR03
Regular replenishment
1Rp 243.9M27 Aug 2026402 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Apr 2026MediumPX_KC-853DLeak from packing
13 Apr 2026LowPX_KC-853DLeak from packing
02 Dec 2025MediumPX_KC-853DReplace lamp as per PM finding
27 May 2025LowPX_KC-853DRepair insulation KC-853D

Recent goods issues

Posting dateQtyOrderOrder type
16 Apr 20261201000025702Corrective